Monday, November 15, 2010

Metwood Truss and Garage



The photo above shows a boom operator hoisting a metwood truss into place on a concrete basement wall. The truss is held by a high strength rope that can hold heavy objects. The truss was picked up from the delivery truck and then moved to the slab. Laborers were in the basement with a 2x4 to help steady the truss to set it into place.




Once the truss is set, W-pans are set on top of the trusses to pour the concrete on. The pans over various depths so that the the concrete will be structurally sound throughout. The pans are shaped so that they can tie into each other on each end. The right side will clamp into the left so that the pans will act as one unit.

Sunday, November 14, 2010

Rigid Vs. Moment


On this exterior frame, the horizontal I beams are connected with bolts to a flange in the metal column. The difference between a rigid and moment connection is a bolt to weld connection, respectively. A rigid connection is made so that movement is allowed. The bolt from the beam to column allows for rotation of the beam when the building moves. A moment connection welds part of the beam to the column so that there isn't any movement. The contractor will "call out" why type of connections are to be made on the plans for each connection.

This is another photo, although harder to tell, of a rigid connection. This I-beam is used as a header over a door opening. A hole is drilled through the flange on beam, and a bolt is inserted through into the CMU. A washer and nut are then used to lock the beam into place.
If you notice, the beam doesn't sit flush with the CMU wall. This is because there needs to be a gap so that when there is movement(in most cases it is dealing with the heating and cooling of materials which causes expanding and contracting). If the beam were to sit flush with the CMU, it would put pressure on the interrior wall when the beam expanded in hotter temperatures. This could cause damage, most likely cracking, with the interrior wall.

Wall to Contrete



Have you ever wondered how you tie a wall into concrete? The wall cannot just sit on top of the concrete, it has to somehow be nailed into the concrete. How does this process happen? Hammering a nail into the concrete will end up going no where, and you can't screw in the nail; the concrete is too hard.

In order to nail a wall system into the concrete you can use a ramset(looks like a dewalt pistol) that fires a .22 caliber bullet into a nail which gives the nail enough power to drive through the concrete. I was able to experience this process this past weekend. We were putting up a cage that would hold propane tanks into an already existing old brick wall. Although this method didn't work, due to the inconsistency with the brick in the wall, it was awesome watching the process. Below is a photo of what a ramset looks like, as well as the nails that it uses.













You can use ramsets on wood and metal framing. Thus, this method works on both residential and commercial projects.

Ramset photos were taken form left to right- 1) http://www.nextag.com/RAMSET-ITW-Ramset-2-510293463/prices-html
2)http://www.getprice.com.au/Ramset-Powder-Actuated-Fastener-JOB-MASTER-GAS-Gun-Gpnc_503--46910865.htm

Friday, November 12, 2010

Pouring a Slab




This is a close up photo of a recently poured slab for a garage on our residential site. In order for your slab to be correctly constructed, a few proper steps must take place. The earth which you are pouring your slab should be tamped, or compacted, so that your sand and gravel bed has a flat surface to sit on. Next, gravel is brought on site and leveled out in the area that the concrete will be poured. The gravel is normally 4" thick. After the gravel has been spread out, a moisture retardant is laid on top. The moisture retardant keeps water from the soil coming up into the slab. If moisture has prolonged exposure to the concrete, it can cause serious problems with the integrity of your slab.
This photo shows the gravel bed, moisture barrier(in yellow) and wire mesh(rebar) in preparation for a slab pour. Once all the components have been properly put into place, a chalk line is used to mark the height of where the concrete is to be poured. In this photo, the chalk line is just above the waterproofed lumber. You can see the chalk line the best in-between the two CMU blocks.

If a slab is being poured where an opening is, such as a garage, there needs to be a mechanism set up so that the concrete doesn't leave the area that it is supposed to. Every time I have seen this done, a piece of lumber is screwed into a metal form. The lumber acts as a barrier to keep the concrete from flowing out of the intended area. On the back of the form, there is a place where you can drive a stake into the ground in order to hold the form in place. Below is a photo that better explains what the form looks like.



Wednesday, November 10, 2010

Anchor Bolts and Wall FD's

Here is the corner of a concrete foundation wall with 3 anchor bolts imbedded in the concrete. Anchor bolts serve an important purpose of tying in the foundation to the floor system. The first step of tying in your foundation is placing a 2x4 or 2x6, depending on what size lumber you want your exterior wall to be. A 2x4 wall is cheaper to frame but will provide less insulation for your building envelope while a 2x6 wall will provide more insulation but will cost more. The homeowner must decide if the upfront cost of framing a 2x6 wall will offset the lower energy costs provided overtime.
Once the owner has decided on the particular framing lumber the framing crew will begin to frame up the house. The 2-by material will be laid flat on top of the anchor bolts. Someone will then take a hammer and pound the lumber into the anchor bolts. This will mark where the anchor bolts lay on the lumber, and an hole will be drilled where the indention is. After all the holes have been drilled, the 2-by lumber will be placed down on the foundation. After placed, the lumber is secured tight by a bolt. This makes sure the lumber can't move and provides a sturdy base for the walls to sit on.
It is of utmost importance that the sill plate(2-by lumber) is termite treated. This will prevent ants from eating away the lumber and getting into your walls. One could only imagine the damage that termites could do to a wall system.


This is what the finished product should look like. The sill plate is attached to the wall system. In this scenario, prefab floor joists have been set on top of the basement foundation. These particular trusses allow for conduit and HVAC to be run underneath the floor system. I would assume that holes will be cut into the floor sheathing, once the house is dried in, for floor vents.




Tuesday, November 9, 2010

Joints, Joints, and more Joints...

The split in CMU, concrete masonry unit, that you see above is a separation joint. Separation joints are used to allow movement within the building. These joints need to be placed every 250' or less in order to meet code. In this scenario, where the joint is near an opening, it is likely that the contractor or architect wants to keep the opening from moving with the other interior wall. The adjacent wall may have more load than wall with the opening, thus, you would want to keep these walls separate when the building starts to move.

Keep in mind, when I talk about movements, these aren't 4' or 5' shifts in the ground. These movements are hopefully unnoticeable to the eye and are only micro-movements within the soil.

To connect the gap in the wall, a backer rod is shoved in the gap no more than half the distance of the width of the gap. IE- if the gap is 2" wide, you would place the baker rod 1" into the gap. The easiest way to explain the backer rod is a miniature "noodle" that you would play with in the pool.

This is a picture of someone placing a backer rod in a joint on the ground. Once the backer rod is placed in the wall, you need to take in mind adhesion and cohesion. Adhesion is the ability for materials to bond to a foreign substance and cohesion is the ability for materials to stick or stay together. You ultimately want a good balance of adhesion and cohesion so the joint won't have problems with cracking. If you have too much adhesion or cohesion the bond will end up breaking or cracking and the joint will be weak.

The last image was taken from - http://www.move.com/home-garden/do-it-yourself/masonry-concrete/replacing-expansion-joints.aspx

Monday, November 8, 2010

Wet or Dry?

This is a photo is of drain tile running along a concrete foundation in a benched footing excavation. Drain tile is used for re-routing water that has fallen close to the foundation. The drain tile is semi-permeable and allows water to enter without other particles following suit. In this picture, an L-connector is used to connect the two pieces at the foundation corner.

The drain tile runs the perimeter of the house and then exits the yard in the lowest corner. In order for the tile to be hidden, a trench is dug to conceal the tile. This allows for gravity to cary the water from a high to low point.

Once the drain tile is laid, crush-n-run stone is dumped on top of the tile, normally 4" depth. This helps to act as another permeable shield to keep out larger particles and allow only water to fall down.